The commissioning is done by DMI's teams or it's representative.

As most of the elements supplied by DMI are skid-packaged, the commissioning is easy and very time efficient (the machine will be made operational in a matter of days).

In addition, the client's staff will be trained in the use and in the maintenance of the equipment during the commissioning.

 

  • Capacity


  • Processed volume per batch

    Estimated number of processed eggs per batch
    Time per batch
    Time to download after process
  • Dehydrator AV500L
  • 500 liters

    10000 eggs
    5 to 7 hours
    10 minutes
  • Dehydrator AV1500L
  • 1700 liters

    30000 eggs
    10 to 14 hours
    15 minutes
  • Dehydrator AV300OL
  • 3800 liters

    75000 eggs
    12 to 15 hours
    15 minutes
  • Dehydrator AV6000L
  • 6800 liters

    130000 eggs
    12 to 17 hours
    20 minutes